Following the completion of upgrades at the 110KV Yujing Substation, Sangpu Campus will switch power loads from the 10KV Diexue Line to the 10KV Yuda Line. Some areas will experience 5–15 minute temporary power outages.

Switching time: June 6 (Saturday), 1:00 PM

Affected areas:

TransformerAffected Areas
Switch Station 1Station 1, East Pump Room
Student DormitoriesBuildings A/B/C/D/L/Y, former boiler room, Canteens 2 & 3, market
Professor BuildingDormitories E/F, Building P
Exchange BuildingShude College, Art College
High-Rise Faculty Apt.High-rise faculty apartments
Faculty HousingA1-A14, B1-B12, kindergarten, hospital, seismic station, union
West Pump RoomWest pump room, middle/high school, B13-B16
AuditoriumAuditorium, lake sewage pump
Admin CenterFormer admin center
Science BuildingScience Building
Engineering BuildingWind tunnel, Engineering Building, East Lecture Hall
Former Medical BldgHigh-level lab, Teaching C/D/G, Social Sciences
Liberal Arts BldgLiberal Arts, AV Building, West Lecture Hall, Physics Lab
Science & Tech BldgScience & Tech Building, Mechanical-Electrical Building
Network CenterNetwork center, foundation office, expert apartments
Old GymnasiumOld gymnasium

Contact: 86502489 / 86502710

Source: Resource Management Office (OA Notice)